Primary Mill Infrastructure Aldwarke

Primary Mill Infrastructure Aldwarke

Project Factsheet

Client

Corus

Location

Rotherham

Duration

25 weeks

Value

£2,240,000

The project comprised extensive civil engineering works to provide infrastructure at the Primary Mill Development, Aldwarke, Rotherham.

Extensive reinforced concrete structures included tank bases, pumphouse bases, transformer house, and associated works such as casting pits, ducts, chambers, muck pen and mold tower.

The 23 week project is one amongst many undertaken at several Corus plants throughout the region.

Project Gallery

Primary Mill Infrastructure Aldwarke
Primary Mill Infrastructure Aldwarke

Projects

  Page 1 of 1 

Project Libra (Corus)

Project Libra (Corus)

Civil Engineering works required for Project Libra at the Corus Steel plant in Scunthorpe (now TATA steel) were provided by Britcon on a 'design and build' basis. The required works were associated with the transfer of the furnace from the Heavy Section Mill to the Medium Section Mill and the associated Cooling Bank Extension works.

Works undertaken by Britcon comprised general site preparation and service diversions, piling to the foundations for the furnace end and cooling banks, foundations for the furnace, the furnace building and cooling bank building foundations, electrical substations, hydraulic house basement, scale pit, discharge and charging roller table flumes, water treatment bank civil works, emergency water tank civil works and general civil works.

Project Libra's objectives were to enhance the Medium Section Mill to enable railway sections to be rolled to achieve a top 3 manufacturing placement for Corus in Europe.

The Medium Section Mill remained in production throughout the contract period.

Read more about Project Libra (Corus)...

Project Libra (Corus)

Civil Engineering works required for Project Libra at the Corus Steel plant in Scunthorpe (now TATA steel) were provided by Britcon on a 'design and build' basis.