Anaerobic Digestion Plant

Anaerobic Digestion Plant

Project Factsheet

Location

Prosper de Mulder Refood

Duration

40 weeks

Value

£6,000,000

Britcon were engaged as principal contractor to construct a state of the art anaerobic digestion facility capable of converting in excess of 45,000 tonnes of food waste into power generating methane gas to be used as a fuel source for the adjacent feed processing factory with excess power being fed back into the local electricity grid network, producing overall 2.8Mw of renewable electricity and heat, enough to power about 5,000 homes.

The anaerobic digestor takes 25-36 days to complete its cycle. As well as heat and electricity, it produces 43,000 tonnes of odourless organic fertiliser a year, which is sent to local farms.

Our client was Prosper de Mulder Ltd. in partnership with their European anaerobic digestion plant operators SARIA who have a number of similar installations on the continent.

PDM were keen to use local supply chains and as such invited local companies to tender for the project. Britcon were selected as principal contractor. On appointment, Britcon engaged in an intense process of value engineering to ensure 'best value' had been achieved throughout the entire project providing civil engineering infrastructure and construction of a new dedicated office and amenities block for the AD plant, which is highly energy efficient, in line with the rest of the project.

The initial phase was a relatively straight forward earthworks re-engineering of the top 2m of the existing brown field site to bring the formation to a suitable bearing capacity for the structures to be constructed but this did incorporate a major dewatering of the temporary works for the deep basement which was a considerable depth below the adjacent river level.

On completion of the earthworks and piling operations, the major structures which comprised multiple high rise post tensioned circular reinforced concrete digestion tanks, receiving tanks and gas storage tanks along with numerous process structures, extensive external works and administration office commenced.

The concrete tank structures were sub-contracted to a nominated Austrian specialist slip forming contractor utilising their own patented shutter / integrated rotating equipment.

Given that the administration office was to be used in conjunction with a green energy plant, the brief was to create an office facility that was as environmentally friendly as possible, using the latest sustainable methods of construction. With this in mind the materials were sourced to provide maximum recycleability over the whole life cycle of the building.

Thermal values of all elements of construction were closely considered, with the eventual building envelope far exceeding the requirements of the Building Regulations. Internal walls and the inner leaf of the external walls were formed with dense masonry to provide high thermal mass; to be used in conjunction with a night-time cooling strategy, fresh air is brought into the building overnight to cool the dense structure which slowly absorbs heat through the day. In winter the air is not extracted and thus stays warm.

Architects, John Hill Associates from Doncaster, managed the design and construction throughout the build process.

Project Gallery

Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant
Anaerobic Digestion Plant

Projects

  Page 1 of 1 

Grain Storage, Drying and Cleaning Infrastructure

Grain Storage

The 24,00-tonne storage, dying and cleaning complex, built at Muntons malt manufacturer's Flamborough site near Bridlington, was set up to protect the continuity of supply and demand for quality British malting barley.

English Farming and Food Partnership brokered a deal between Muntons Malt and two farmer co-operatives - Openfield and GrainCo - to build the complex, which promises some significant environmental benefits. The barley drier alone is said to cut CO2 emissions by around 650 tonnes per year compared with farm-based drying.

A new company, Muntons Malt Supply Chain, will operate the site and it has already secured new contracts with farmers and Muntons, major distilling and brewing customers.

Muntons' general manager Guy Newsam said: "We are proud to be a major player for an innovative solution for the secure movement of quality malting barley. The key aim of the MMSC is to help growers understand the requirements of all partners in the brewing industry and deliver smart supply chain solutions."

Britcon's work comprised site access roadways, intake and cleaner building infrastructure, drainage and interception pits, 6 heavily reinforced concrete silo bases, weighbridge infrastructure and numerous foundations, support pads and ductways.

Read more about Grain Storage, Drying and Cleaning Infrastructure...

Grain Storage, Drying and Cleaning Infrastructure

The 24,00-tonne storage, dying and cleaning complex, built at Muntons malt manufacturer's Flamborough site near Bridlington, was set up to protect the continuity of supply and demand for quality British malting barley.

  Page 1 of 1