New Perimeter Footpath, Baysgarth Park South

  • Form of Contract

    Form of Contract

    N/A

  • Client

    Client

    North Lincs Council

  • Architect

    Architect

    N/A

  • Engineers

    Engineers

    North Lincs Council

  • Programme

    Programme

    18 Weeks

  • Completion

    Completion

    April 2020

Works Scope

The works consisted of a new 1.6km footpath, through a live public park, to improve recreational facilities for park users both on foot and ambient. The works including traffic management to accommodate phasing of the works (to maintain live public services) excavation of new porous pathways and seating benches, signage and drainage together with grass seeding and planting reinstatement.

Key Project Challenges

  • Phased work operations
  • Live interface with Park Users
  • Ecological protection

How we successfully delivered the project

  • Increased work phases allow park to remain open
  • Public notice board and website communicating works